Control Engineering Asia

Sponsored Links

Ads by Google

Add a Comment

» Post A Comment Now!

There are no comments for the article yet.
Rate this Article

Current Rating:
No rating yet

Excellent
Very Good
Good
Quite Good
Poor

Rate this Article Now!

Related Stories

Invensys Aims to Double Revenue from the Middle East - 21 February 2008


Industrial process control automation company Invensys aims to execute contracts worth US$1 billion in the Gulf in five years, its vice-president and m

Dual Redundancy in Eurotherm T2550 Control Unit - 18 February 2008


Eurotherm's T2550 control unit has automatic dual redundancy options, that it claims, improves process efficiencies and protects against controller or

Emerson Invests in Energy Responsible Automation - 18 February 2008


Emerson Process Management has announced its latest new products from ongoing investments in energy responsible technology. It also reviewed


How keen are you to install wireless instruments in your plant?
Very, I see many possible applications
Would prefer to wait for technology and standards to mature
Not at all, I have serious reservations about plant wireless
View results
Ask a Question

Free Magazine Subscription    Printer-friendly version    Email to a Friend

           

DCS Adds Control to Mongolian Power Plant

-- Top News, 6 June 2006

Jeanine Katzel, senior editor Control Engineering US

Ads by Google

Distributed control system (DCS) technology installed at the new combined-cycle power plant at the Solig Gas Power Co. Ltd. facility in Inner Mongolia is performing balance-of-plant control. The system, supplied by GE Energy, links to a 126-MW GE PG9171E gas turbine controlled by a Mark VI control system. Announcement of the contract and installation was made at Power Gen Europe 2006.
A comprehensive equipment and service package, also provided by GE Energy under a separate contract, included gas turbine and long-term supporting services. The DCS controls heat recovery steam generators, the electrical system, and circulating water controls for Inner Mongolia's #1 and #2 units. The control system for unit #1 began commercial operation April 24.
The Solig project is the first gas-powered generation plant in Inner Mongolia. The effort, launched in October 2004, includes two sets of combined-cycle units. Unit #2 is expected to go into operation early in July.
www.manufacturing.net

           